4 men and 10 women were put on a work. They completed 1/3 of the work in 4 days. After this 2 men and 2 women were increased. They completed 2/9 more of the work in 2 days. If the remaining work is to be completed in 3 days, then how many more women must be increased ?



[ A ]    32
[ B ]    8 right
[ C ]    50
[ D ]    55
[ E ]    None of these
Answer : Option B
Explanation :